CONSTRUCTION OF TWO MINI WATER YARDS IN MABAN SOUTH SUDAN

CONSTRUCTION OF TWO MINI WATER YARDS IN MABAN SOUTH SUDAN

Aptech recently designed, supplied, installed and commissioned two constructions of two mini water yards with boreholes equipped with solar powered pumps, elevated tanks and tap stands in Maban Upper Nile state in a project funded by the United Nations International Children’s Emergency Fund-(UNICEF).

The pumps were installed at two sites, one at Hai Dome, another at Hai Bagdad. At each of the two sites, boreholes of 100M were drilled with borehole yield of 2.0m3. Thereafter each of the sites was equipped with a 2.04kWp of Soleil Power panels, very sufficient to efficiently run the DC brushless motor attached to the Lorentz PU1800-CSJI-25, Lorentz pump.

At each site two 5000L plastic tank were installed on steel water towers to store 10,000litres per day. The welding works for the steel water tank stand were executed very successfully without any hardships and the works are expected to last for at least 5 years without any need for repair. One layer of the red oxide paint as well as two layers of the final coat were carefully applied on each metallic surface of the tank stand.

Also fencing works for the water yard were executed successfully and the perimeter fence was well equipped with access door. The borehole, the steel water tank stand and plastic tanks and all the power electronics of the system including the solar generator are fully enclosed within the perimeter fence with one round of razor wire installed for additional security.

The water distribution in the area involved installation of two water collection points with ¾ inch size taps at each location which were fitted with a small trough at the tail end of each drainage channel. A total of 6 ball valve taps were installed at each of the water collection points

At Hai Bagdad, one water collection point was installed at 50m away from the storage tanks and the second water collection point was installed 200m away from the water tank with an 11/4inch HDPE pipe buried 500mm below ground level.

At Hai dome, one water collection point was installed at 90m away from the storage tanks whereas the other water collection point was installed 200m away from the water yard all connected with 11/4inch HDPE pipe buried 500mm below ground level.

Aptech Africa Co. Ltd was tasked to solarize these two boreholes in Jamam which is one of the three payams in Maban County with its administrative headquarters in Jamam town. The town is estimated to have a population of 12,000 people and host to at least 33,000 refugees from the Blue Nile region of Sudan.

Given the climate conditions of the area being dry most of the year causing less availability of water for domestic supply, we therefore expect optimum performance from the solar pump installations which is reliable and sufficient which intern will ensure that the community is well served with clean drinking water at all times

About Author

Related posts